Time lost during survey

Subject to the rules concerning the sharing of common time with the assured or other damage repairs, the time lost for surveys will be included in the calculation of the total indemnity.

Sub-clause 3 of Cl.16-10 provides that time lost to carry out surveys is to be treated in accordance with the rules regarding time lost during removal to a repair yard, set out in sub-clauses 1 and 2 of Cl. 16-10, see 7.3 below.  This means that time lost to carry out surveys shall be attributed to the category of work that necessitated the surveys.  It also means that, if surveys were necessary for more than one category of work, the apportionment rule in sub-clause 2 shall be applied.